Pier Foundations

Strategy Briefing

Market Conditions, Risk Mitigation, and Contract Pipeline
May 22, 2026 Prepared by Peter (AI COO)
Section 1

Current Market Conditions Affecting Pier Foundations

Tariff Impact on Construction Materials

Material Tariff / Increase Impact
Steel 50% tariff Up 20.7% year-over-year
Aggregate / Concrete No direct tariff 4-6% increase expected through 2026
Overall Construction Inputs Multiple tariff categories Surged 12.6% annualized (fastest since 2022)
Total Project Costs -- Up approximately 3-6%

Key Insight: Steel-heavy deep foundations get MORE expensive under tariffs, making Pier Foundations' VSC solution MORE competitive. Our existing 30-50% cost advantage over traditional deep foundations widens as steel prices rise.

IIJA Funding Cliff Risk

Metric Status
IIJA Authorization Expiration September 30, 2026
Allocated So Far $568B of $1.2T total (47%)
Already Rescinded $2.3B
Remaining to Allocate $492B

If Congress does not reauthorize: Unobligated funds for discretionary programs expire and new lettings pause. However, projects already under contract continue getting paid.

The next highway bill is expected to be "significantly higher" than IIJA (per Granite Construction CEO), but timing remains uncertain.

Section 2

Government Relief Mechanisms

Federal Level

State DOT Price Adjustment Clauses

Material % of State DOTs with Adjustment Clause
Fuel 84%
Asphalt 80%
Steel 36%
Cement 6%
Aggregate Not typically covered

Note: Most clauses require a 5% price swing to trigger. Aggregate -- Pier Foundations' primary material -- is NOT typically covered by price adjustment clauses.

Indiana State Incentives

Recommended Actions

  1. Add ConsensusDocs 200.1 price escalation clauses to every private contract
  2. Verify INDOT's specific price adjustment clause provisions before bidding DOT work
  3. Lock in aggregate pricing with suppliers (Midwest Quarry in Woodburn, 15 miles from Fort Wayne)
  4. Monitor IIJA reauthorization closely
Section 3

Lock In Revenue Before September 30

With 4 months until IIJA expires, the strategy is simple: bid aggressively on public work now (these contracts get paid even if funding lapses), while simultaneously building private-sector relationships that don't depend on government funding at all.

Tier 1 -- Public Infrastructure (IIJA-Funded)

INDOT Remaining Lettings Before Deadline

Letting Date Status Action Required
July 8, 2026 Coming -- new electronic bidding starts Register on Bidx.com NOW
August 5, 2026 Coming Monitor for bridge/foundation work
September 2, 2026 Last before IIJA expires Bid aggressively

INDOT Electronic Bidding Migration: INDOT is migrating to Bidx.com starting June 10. Registration required. Contact: John Wooden at INDOT (317-233-5743 / jwooden@indot.in.gov)

Ohio DOT: Record $3.4B construction season, 977 new projects, 739 bridges.

Tier 2 -- Data Centers (Private, No Government Dependency)
Project Value Timeline General Contractor
Google Fort Wayne (Project Zodiac) $2B+ Active development TBD -- identify GC and geotech engineer
Meta Lebanon (Project Domino) $10B Broke ground Feb 2026 Mortenson + Turner
Cologix Ohio $7B total campus Phase 1 underway TBD
CoreWeave Hammond 180 MW Pre-construction TBD

Opportunity: A single data center building = $200K-$1M+ in ground improvement work. These projects run 2-5 years. Completely independent of IIJA funding.

Tier 3 -- Private Commercial
Project Location Value / Size
Neighborhood Infrastructure Fort Wayne $37M ($28.4M roads/bridges)
Electric Works Phase II Fort Wayne 296 units + commercial
The Landing Exchange Fort Wayne 40 units + 5,000 SF commercial
Amazon Fulfillment Center Greenfield, IN 1M SF
IU Health Academic Center Indianapolis Multi-phase through 2027
Stellantis Engine Plant Kokomo, IN $100M+
Tier 4 -- Adjacent State DOTs
State Opportunity Monitoring Link
Ohio $3.4B season, 977 projects, 739 bridges ODOT Contracts & Proposals
Michigan 2026-2030 Five-Year Program MDOT Projects & Studies
Illinois Monthly lettings, $10.3B data center spending IDOT Letting and Bidding
Section 4

Priority Actions -- Next 30 Days

  1. Register for INDOT electronic bidding on Bidx.com Brad -- before June 10
  2. Verify INDOT prequalification status is current Brad
  3. Add price escalation clauses to all new contracts (use ConsensusDocs 200.1) Brad
  4. Lock aggregate pricing with Midwest Quarry for 6-12 months Brad
  5. Identify GC and geotech engineer for Google Fort Wayne data center Peter
  6. Contact Mortenson/Turner re: Meta Lebanon subcontractor opportunities Brad + Peter
  7. Pull INDOT 18-month letting list for July-September opportunities Peter
  8. Monitor ODOT and MDOT bid boards weekly Peter
  9. Begin outreach to target GCs: Pepper Construction, Hagerman Group, Shiel Sexton, Barton Malow Brad
  10. Track IIJA reauthorization progress -- flag any developments Peter
Section 5

The Bottom Line

The market is moving in Pier Foundations' favor: tariffs on steel make our VSC solution more cost-competitive, and the Midwest is experiencing unprecedented construction demand from data centers, infrastructure, and industrial development. The risk is a potential public funding gap if IIJA reauthorization stalls. The mitigation is straightforward: lock in public contracts before September 30, build private-sector data center relationships that don't depend on government funding, and protect margins with price escalation clauses and locked-in material pricing. The worst position is an empty pipeline in Q1 2027.